That Tuesday at the paper mill in Pineville made me rethink how we load tube bundles
We were pulling a superheater bank on a Tuesday and everything went smooth for once, which almost never happens. The crane crew had the bundles out in 45 minutes instead of the usual 3 hours, and the foreman gave us the rest of the afternoon to inspect the drums. I think the whole thing worked because we cut the lift plan down to one page and everyone actually read it before the shift started. Other crews I have been on hand out 12 page lift plans nobody looks at. What is the shortest lift plan you have seen actually work on a job?
Forty five minutes versus 3 hours is a huge gap, so something in that one pager clearly clicked with the crew. When you cut it down, did you drop the step by step rigging sequence and just keep the load weights and pick points, or did the crew fill in the rest at the pre shift talk? I am asking because on a drum job last spring we went to a single page and the older hands said it was too thin on the tag lines.